With WBS Gantt-Chart, holidays and non-working days are taken into account when creating/modifying plans. Follow these steps to configure non-working days.
WBS Gantt-Chart ⇒ Choose Gantt Configure.
...
Click Edit of Calendar.
Edit holiday calendar settings:
If there are no regular holidays, check Irregular holidays;
If there are regular holidays, select 1st regular holiday, or 2nd regular holiday, according to the number of non-working days;
For individual holidays, enter each day under Holiday in the format YYYY-MM-DD;
Click Update.
You’ve now completed the basic configuration. Next, let’s try managing a project.