Basic method for updating the progress rate
Click % Done to open Edit mode. Then you can either click the up/down arrows or directly enter a value.
...
However you cannot edit the progress rate for:
A project or version
Issues in gray color
Auto-calculating parent issue progress rate
You may want to synchronize the progress rate between parent and child issues. This would mean, for example, that when the progress rate of a child issue is 100%, the parent issue's progress rate will also be 100%. You can do this with Auto-calculate percent done.
...
The calculation of the progress rate is based on time spent and duration. For
...
example
Issue A has a duration of
...
1 day with 100% done
...
Issue B has a duration of
...
2 days
...
with 50% done
...
The total progress rate of parent issue
...
would be:
Code Block |
---|
(100% * 1 day + 50% * 2 days) / (1 day + 2 days) = 66% (Decimals are rounded down) |
...
...
There is a special case.
The progress rate of the parent ticket is calculated as 100%
However, there is a child ticket with a blank duration and progress rate < 100%
In this scenario, the parent's progress rate will be adjusted to 99%
...