Versions Compared

Key

  • This line was added.
  • This line was removed.
  • Formatting was changed.
Panel
titleOn this page:
Table of Contents
maxLevel3
printablefalse

Displaying the planned Gantt bar of the currently selected row

Select a row and do one of the following with the row on WBS side being displayed in yellow:

  • Click Jump to Gantt Bar on the operations toolbar

  • Click Jump to Gantt Bar in the context menu

  • Press keyboard shortcut b

If the start date in the target row is already entered, the Gantt chart jumps to the position of the start date. If only finish date is entered, the Gantt chart jumps to the finish date.


Displaying today's date

Click Today on the operations toolbar.


Time display units and time periods (display period)

Click on << or >> on the toolbar. The time period moved forward or backward depends on the time unit displayed . 

Time display unit

Display period

Day

7 days

Week

5 weeks

Month

3 months

Quarter

4 quarters

Year

5 years




Changing a display unit

  1. Click the current Unit on the operations bar.

  2. Select one of the Units in the menu. 


Time display unit

Display period

Day

70 days

Week

30 weeks

Month

12 months

Quarter

20 quarters

Year

25 years

Bird's-eye view 

The Gantt chart spans all Gantt bars


Info

Two ways of displaying units for weeks

Weeks can be displayed in two ways: either by the start date of the week or the number of the week.


Info

Display of fiscal year

Quarters are displayed based on the starting month of the fiscal year that is set. For example, if the start month of the fiscal year is March, the first quarter (Q1) is March to May.


 









Include Page
Any questions?
Any questions?