Versions Compared

Key

  • This line was added.
  • This line was removed.
  • Formatting was changed.
Panel
titleOn this page:

Table of Contents
maxLevel3
printablefalse

Basic method for updating the progress rate 

Click % Done to open Edit mode. Then you can either click the up/down arrows or directly enter a value.

...

However you cannot edit the progress rate for:

  • A project or version

  • Issues in gray color

Auto-calculating parent issue progress rate 

You may want to synchronize the progress rate between parent and child issues. This would mean, for example, that when the progress rate of a child issue is 100%, the parent issue's progress rate will also be 100%. You can do this with Auto-calculate percent done.

To use this feature, you need to enable Auto-calculate percent done in user preferences. For more information on user preferences, refer to this document.

Note

Auto-calculate percent done cannot be enabled unless Auto-correct schedule is enabled.

...

The calculation of the progress rate is based on time spent and duration. For instance, if Issue A has a duration of one day with 100% done, and Issue B has a duration of two days of with 50% done, the total parent issue progress rate would be:

...

Code Block
(100% * 1 day + 50% * 2 days) / (1 day + 2 days) = 66% (Decimals are rounded down)

As shown in the progress bar, the one day issue has 100% percent done with all work for the day completed. The two day issue has 50% done, with one day's work completed. Therefore, for the parent issue, two days out of three are completed, equating to 66% done.

Include Page
Any questions?
Any questions?