Jira field | Microsoft Project field | Notes |
---|
Summary | Task name |
|
Assignee | Resource name | |
Workload |
Start date | Start date | Uses the value of the field configured as "Start date in WBS Gantt-Chart for Jira |
Finish date | Finish date | Uses the value of the field configured as "Finish date" in WBS Gantt-Chart for Jira |
Baseline start date | Standard start date | Uses the value of the field configured as "Baseline start date" in WBS Gantt-Chart for Jira |
Baseline finish date | Standard finish date | Uses the value of the field configured as "Baseline finish date" in WBS Gantt-Chart for Jira |
% done | % complete | Uses the value of the field configured as "% done" in WBS Gantt-Chart for Jira However, in Microsoft Project, the % completion rate of a summary task is automatically calculated including accumulated % completion of child tasks as well. Therefore the value shown may differ from % done in WBS Gantt-Chart for Jira. |
Due date | Deadline |
|