Go to edit mode of the Gantt chart.
Open the configuration panel.
Switch tab to calendar.
Manage Edit working days and extra holidays.
Close the configuration panel by clicking the update button.
...
The table below shows the number of days per 1 duration unit in each case of the number of working days. Please note extra holidays do NOT affect the meaning of the duration units.
DurationNumber of working days | 7days | 6days | 5days | 4days | 3days | 2days | 1day |
---|---|---|---|---|---|---|---|
1 Week equals | 7days | 6days | 5days | 4days | 3days | 2days | 1day |
1 Month equals | 30days | 25days | 20days | 16days | 12days | 8days | 4days |
...
Example
Your Gantt chart has 5 working days as Monday, Tuesday, Wednesday, Thursday, and Friday like the image below.
...