Updating plans
...
This feature is always enabled in WBS Gantt-Chart for Jira Cloud.
If you want to control cascade changes , see for each issue, please refer to "Switching off Auto-correct schedule" on this page.
...
This feature is always enabled in WBS Gantt-Chart for Jira Cloud.
If you want to control auto-correction , see for each issue, please refer to "Switching off Auto-correct schedule" on this page.
...
Select the issue you want to convert.
Select Edit in the operations toolbar ⇒ Choose Convert to milestone or Convert to regular task.
Baselining issues
Note |
---|
We recommend you get agreement on the plan from all involved parties (such as the project owner) before baselining. |
Info |
---|
When an issue is baselined, the baseline bar is automatically displayed. |
...