When you plan a project schedule, you will want to plan who will do tasks. You can assign Confluence users or defined custom resources to tasks in the Gantt chart and see the workload of users.

...

.

...

How to define custom resources

  1. Show the resource view.

  2. Click the plus icon on the top of the resource view.

  3. Set the name and avatar color to the added resource.
    Please double-click the cell to edit the name or avatar color.

...

How to assign resources to tasks

  1. Show the resource column if the column is hidden.

  2. Double-click the cell of the resource column to start editing.

  3. Search and add the users or custom resources you want to assign.

  4. Change units if the users won’t spend the entire time of work.

...