If Gantt Chart Planner helps you to have accurate scheduling and resource assignments using this formula.

“Duration * Assignment units = Effort”

...

For example, if a task takes one day of effort and its duration is four days, the assignment units of a resource would be 1 / 4 = 25%.
Therefore, the relationship can be expressed as “duration * assignment units = effort”.Gantt Chart Planner helps you to have accurate scheduling and resource assignments using this formula.

The one rest parameter is automatically calculated when you set two of three parameters.

...

On the formula above, if you change the duration, either assignment units or effort should be recalculated. Effort mode decides which one will be recalculated.
The table below explains which parameter will be recalculated in each effort mode.

...