When Clicking the name, open the Jira issue page.
The issue type icon is displayed in the Name column.
If the linked issue has been resolved, the resolution icon appears next to the task name.
The issue status is displayed in the Status column.
The % Done is automatically updated based on the issue status and the time tracking.
When the linked issue status has been resolved, the % Done will automatically update to 100%.
The % Done is automatically updated by Time Spent / (Time Spent + Time Remaining).
These are optional. You can toggle this option in the Jira integration configuration.
If Jira field mapping is configured for the start and finish dates, those Jira fields are updated to the task’s start and finish dates when creating a Jira issue from a task or saving the Gantt Chart.
Note |
---|
To use Jira field mappings, you need to place those Jira fields to the create screen and edit screen. |
...
How to link Jira issues to tasks
...