Versions Compared

Key

  • This line was added.
  • This line was removed.
  • Formatting was changed.

...

  1. WBS Gantt-Chart ⇒ Choose Gantt Configure.

  2. Click Edit of Calendar

...

  1. Edit holiday calendar settings:

    1. Choose using shared calendar or Gantt individual settings calendar

    2. Check the non-working days in Regular holiday

    3. Choose Week Number style (US or ISO-8061)

    4. For individual holidays

...

      1. Enter them to the Holiday list

      2. Or import the holidays from public calendar.

    1. Click Update.

You’ve now completed the basic configuration. Next, let’s try managing a project.

...