The percent done is based on WBS Gantt-Chart data. You can edit these values in WBS Gantt-Chart.

...

(Option) When an issue is resolved, the percent done automatically becomes 100%

If this option is enabled, the value stored in the percent done field is ignored for resolved issues, and the percent done is treated as 100% on the Gantt chart.

Calculate with time tracking automatically

...

How to adjust duration, effort, and units automatically.
This is the default value. Each issue can override it.

Mode

Description

Manual

This mode allows the user to manually enter the Duration, Units, and Effort values.

Effort adjusts

This mode automatically calculates the value of the Effort column using the Duration value * Units value formula.
Manual editing of the Effort column will be disabled.

Info

Example

  • Duration = 8 hours

  • Units = 50%

→ Effort = 8 hours * 50% = 4 hours

Duration adjusts

This mode automatically calculates the value of the Duration column using the Effort value / Units value formula.
Manual editing of the Duration column will be disabled.

The Finish column is also disabled for manual editing, since the values of Start and Duration automatically determine the value of Finish.

Info

Example

  • Effort = 16 hours

  • Units = 25%

→ Duration = 16 hours / 25% = 64 hours

Units adjusts

This mode automatically calculates the value of the Units column using the Effort value / Duration value formula.
Manual editing of the Units column will be disabled.

Info

Example

  • Effort = 8 hours

  • Duration = 32 hours

→ Units = 8 hours / 32 hours = 25%

Please refer to the page below for an explanation of each column.

...