Versions Compared

Key

  • This line was added.
  • This line was removed.
  • Formatting was changed.

Map Jira fields

To sync the task schedule between Confluence Gantt Chart and Jira, you need to map the Gantt start and finish dates with corresponding Jira fields.

The mapped Jira fields must be added to the editing and creating screens so that the app can update the field values. You might need to contact your Jira admin to configure the screens.

  • When you update the Jira date fields, these changes will be shown automatically in Gantt view mode

  • When you open the Gantt editor, you’ll be prompted to save the new synced date. You’ll see an indicator on the task with new synced dates:

...

Info

Auto-scheduling mode will be disabled for synced Jira tasks (Jira to Gantt sync)
When you manage tasks based on the synced Jira date fields, the auto-scheduling mode will be disabled. Open the “Mannually Scheduled” column and uncheck this option to re-enable auto-scheduling, this option will override changes from Jira.

If you have questions or requests, please raise a ticket via our support portal.