Basic method for updating the progress rate 

Click % Done to open Edit mode. Then you can either click the up/down arrows or directly enter a value.

...

However you cannot edit the progress rate for:

  • A project or version

  • Issues in gray color

Auto-calculating parent issue progress rate 

You may want to synchronize the progress rate between parent and child issues. This would mean, for example, that when the progress rate of a child issue is 100%, the parent issue's progress rate will also be 100%. You can do this with Auto-calculate percent done.

...

The calculation of the progress rate is based on time spent and duration. For

...

example

  • Issue A has a duration of

...

  • 1 day with 100% done

...

  • Issue B has a duration of

...

  • 2 days

...

  • with 50% done

...

The total progress rate of parent issue

...

would be:

Code Block
(100% * 1 day + 50% * 2 days) / (1 day + 2 days) = 66% (Decimals are rounded down)

...

...

There is a special case.

  • The progress rate of the parent ticket is calculated as 100%

  • However, there is a child ticket with a blank duration and progress rate < 100%

In this scenario, the parent's progress rate will be adjusted to 99%

...