Exporting to Microsoft Project
You can export projects, versions and issues displayed in WBS Gantt-Chart as XML files that are readable in
...
Microsoft Project by clicking Data ⇒ MS Project export on the operations bar.
The
...
Microsoft Project field for each Jira field is shown in the table below.
Jira field |
---|
...
Microsoft Project field | Notes | |
---|---|---|
Summary | Task name | |
Assignee | Resource name |
|
...
|
...
|
...
| ||
Workload | ||
Start date | Start date | Uses the value of the field configured as "Start date in WBS Gantt-Chart for Jira |
...
Finish date | Finish date | Uses the value of the field configured as "Finish date" in WBS Gantt-Chart for Jira |
Baseline start date | Standard start date | Uses the value of the field configured as "Baseline start date" in WBS Gantt-Chart for Jira |
Baseline |
...
finish date | Standard finish date | Uses the value of the field configured as "Baseline finish date" in WBS Gantt-Chart for Jira |
% done | % complete | Uses the value of the field configured as "% done" in WBS Gantt-Chart for Jira However, in |
...
Microsoft Project, the % completion rate of a summary task is automatically calculated including accumulated % completion of child tasks as well. Therefore the value shown may differ from % done in WBS Gantt-Chart for Jira. | ||
Due date | Deadline |