Versions Compared

Key

  • This line was added.
  • This line was removed.
  • Formatting was changed.

Updating plans

...

If an issue's plan is postponed, the plans of any other issues which depend on this issue can also be postponed. This is done through the Cascade Changes function. To use Cascade Changes, you need to enable it in user preferences. For more information on user preferences, please refer to this document

This feature is always enabled in WBS Gantt-Chart for Jira Cloud.
If you want to control cascade changes for each issue, please refer to "Switching off Auto-correct schedule" on this page.

Image Modified


Auto-correct schedule

...

When issues are edited, you can ensure that the plans of the parent and child issues are updated accordingly using the Auto-correct schedule function.To use .

This feature is always enabled in WBS Gantt-Chart for Jira Cloud.
If you want to control auto-correction for each issue, please refer to "Switching off Auto-correct schedule, you need to enable it in user preferences. For more information on user preferences, refer to this document.

...

" on this page.


...

When a parent issue is moved, child issues are also moved.

...

  1. Select the issue you want to convert.

  2. Select Edit in the operations toolbar ⇒ Choose Convert to milestone or Convert to regular task.

Baselining issues

Note

We recommend you get agreement on the plan from all involved parties (such as the project owner) before baselining.


Info

When an issue is baselined, the baseline bar is automatically displayed. 

...