Panel | ||||||
---|---|---|---|---|---|---|
| ||||||
|
...
Importing Microsoft Project files to Jira
Note |
---|
If you are using Jira 8.4.0 - 8.4.1 Data Center, using this feature will cause an error and will not import issues. This problem is caused by the following bugs in Jira and has been fixed in Jira 8.4.2 Data Center. |
Note |
---|
mpp files saved with MS Project version 2204 (Build 15128.20178) or higher may not be correctly parsed by WBS Gantt-Chart. If you cannot wait for the problem to be fixed, please consider using the workaround described in the portal card below. |
You can import tasks from Microsoft Project as Jira issues by clicking Data ⇒ MS Project import on the operations bar.
In order to use this function, you need to have global administrator permission to "Bulk change" issues .
Each Microsoft Project field is imported as Jira issue field with the following conversion table. The destination Jira field of the planned dates (Start Date, Finish Date, Baseline Start Date, and Baseline Finish Date) and % Complete varies depending on the configurations in the WBS Gantt-Chart for Jira.
Microsoft Project field | Jira field | Notes |
---|---|---|
WBS code | Summary | WBS code and Task name are combined under Summary. |
Task name | ||
Memo | Description | |
Task mode | Manual mode (WBSGantt) | When the Task mode is "manually schedule", the value of Manual mode (WBSGantt) is set as Yes. |
Start date | Field configured as Start Date in WBS Gantt-Chart | If read-only (non-editable) fields such as Created and Sprint are configured in WBS Gantt-Chart, those values will not be imported. |
...
Finish date | Field configured as Finish Date in WBS Gantt-Chart |
Baseline start | Field configured as Baseline Start Date in WBS Gantt-Chart |
Baseline |
...
finish | Field configured as Baseline Finish Date in WBS Gantt-Chart | |
% complete | % done | If % done field is configured as "Calculate with time tracking automatically" or "Calculate with specific fields automatically" in WBS Gantt-Chart, those values will not be imported. |
Work | Original estimate | |
Remaining work | Remaining estimate | |
Resource | Assignee | Searches users registered in Jira in order of "Username" and "Full name." If there is a match, the matched user is selected as the assignee. The import will fail if the selected user does not have "Assignable" permission. |
Deadline | Due date | |
Reporter | Configures the user who performs the import as the reporter. | |
Created | Configures the imported date. | |
Priority | Configures the default priority. |
Include Page | ||||
---|---|---|---|---|
|