Versions Compared

Key

  • This line was added.
  • This line was removed.
  • Formatting was changed.

...

Panel
titleOn this page:

Table of Contents
maxLevel3
printablefalse

Viewing the plan and the baseline

These are shown on the Gantt bars in WBS Gantt-Chart. You can also check the plan start and end dates on the WBS display.

Issues

The plan and baseline dates set in the issue are displayed as Gantt bars. The upper bar is the plan and the lower bar is the baseline.
The difference between these two Gantt bars represents the difference between the current plan and the baseline.

Image Removed

Versions

A version is displayed as a Gantt bar based on its start date and release date. The release date is displayed as a milestone (rhombus shape).

Image Removed

Viewing task delays

Warning alerts are useful for telling you if an issue has started or completed as planned. If there is a colored “!” on the left-hand side of the WBS, that means there is information about the status of the issue.

...

Image Removed

Clicking a warning alert will show the corresponding Gantt bar.

Image Removed

Viewing the progress rate of issues (percent done)

You can see progress for projects and versions on the WBS display. The progress rate is calculated as:

The number of resolved issues (date resolved is set) / the number of all issues * 100

Image Removed

Issue progress rates can be checked via Gantt bars, as well as on the WBS display. If the right-hand edge of a Gantt progress bar is to the left of the vertical dashed line (current date line), that means the task is behind plan. If the right-hand edge is to the right of the date line, the task is ahead of the plan.

Image Removed

Viewing the hierarchy structure 

The WBS display hierarchical structure shows the parent-child relationship of existing issues.
If an issue is displayed in gray this indicates that it is not directly related to the version displayed in the upper hierarchy (hierarchy structure is prioritized for display).

Image Removed

Image Removed

Viewing issue dependencies 

You can check for issue dependencies by looking at the blue arrows displayed between the Gantt bars. If there is a blue arrow from a predecessor issue pointing towards a successor issue, this indicates that the successor issue depends on the predecessor issue.

Image Removed

Types of task links or dependencies

There are four types of task links as follows:

...

Viewing the critical path

Enable Critical path in Tools on the toolbar. The critical path is highlighted, while other task bars and dependencies are shown in a pale color. The WBS display cannot be edited when the critical path is displayed. Issues which are not loaded are not included.

Info
titleWay to make critical paths

Calculation of critical path
The critical path is calculated as follows.

  1. All issues with the latest planned end dates are identified.
  2. Where the issues identified in Step 1 have dependencies, the issues with the latest planned end dates are selected.
  3. Step 2 is repeated for all issues identified in Step 2.

Viewing the resources plan

Click on Resources in Tools on the toolbar. The resources view is displayed on the WBS display and in Gantt chart format.

In the resources view you can display a list of assignees, as well resources bars showing time periods horizontally and % workload (units) vertically. A red line (called a 'limit line') indicates the maximum daily workload.

Image Removed

The resource bar is displayed in green if an assignee's workload units are below or in line with the limit line. If the workload units exceed the limit line, the resource bar will turn red. This indicates that the resources plan needs to be reviewed.

Image Removed

If you move your cursor onto the graph in the resources view, the issues to which the resources are allocated during that period, and their respective workloads, are displayed in a list.

Image Removed

Please note this version contains the following bugs.

  • Issues which do not have planned end dates set are not displayed in the resources view.
  • If there are consecutive resource bars with the same total workload, the resource view tooltip displays the issue list for the first period only.
Info
titleDefault Values of Units

Initial values of workload units depend on how the issues are created.

  • Issues created from projects or versions -> 100%
  • Issues created from issues or issue template -> same value as the original
  • Issues created in Jira -> 100%

Also, when updating from WBS Gantt-Chart for Jira 7.9.1, or earlier, existing issues will have 0% workload units.

...

Child pages (Children Display)
depth5