What is the holiday calendar?
In WBS Gantt-Chart:
Regular (default) holidays are shown in gray.
Project holidays are shown in green.
Holidays are taken into consideration when project start and finish dates are set. All holidays are managed in WBS Gantt-Chart's holiday calendar.
Holiday calendar example
This is an example of the holiday calendar, showing two scenarios, A and B, as follows:
Conditions:
Scenario A
Yes / No |
---|
...
Regular holidays |
---|
...
...
- | |
Holidays | No |
---|
Scenario B
...
Yes / No |
---|
...
Regular holidays | Saturday, Sunday |
---|---|
Holidays |
|
Note: is Monday.
Issue values
Value | |
---|---|
Start date |
|
Finish date |
|
Duration | 2 days |
Operations
Drag-and-drop the Gantt bar so the issue starts on .
Results
Scenario A
This scenario does not have holidays, so the issue values are as follows:
Value | |
---|---|
Start date |
|
Finish date |
|
Duration | 2 days |
Scenario B
In this scenario, , , and will not be counted since they are defined as holidays.
Value | |
---|---|
Start date |
|
Finish date |
|
Duration | 2 days |
Confirm holiday calendar settings
Click Calendars on the left-hand side of the Gantt configuration screen.
Holiday calendar items
...
Regular holidays
You do not set any specific days of the week as holidays.
1st holiday
The first regular holiday you specify. If you select Yes for irregular holidays, this would not be shown.
2nd holiday
...
Check the box for the day of the week to be a fixed holiday.
Holidays
This is a list of the dates you have registered as holidays.
Update holiday calendar
...
Click Edit on the upper right-hand side of the holiday calendar configuration screen.
...
Check the box for Regular holidays.
Enter specific holidays using YYYY-MM-DD format. Enter one date per line.
Click Update.