When Clicking the name, open the Jira issue page.
The issue type icon is displayed in the Name column.
If the linked issue has been resolved, the resolution icon appears next to the task name.
The issue status is displayed in the Status column.
The % Done is automatically updated based on the issue status and the time tracking.
When the linked issue status has been resolved, the % Done will automatically update to 100%.
The % Done is automatically updated by Time Spent / (Time Spent + Time Remaining).
These are optional. You can toggle this option in the Jira integration configuration.
Synced dates from linked Jira issue:
If Jira
Note |
---|
To use Jira field mappings, you need to place those Jira fields to the create screen and edit screen. |
...
Info |
---|
Tip: Select the |
...
start date is later than the current task finish date, the dates will not be mapped
If Jira finish date is earlier than the current task start date, the dates will not be mapped
How to link Jira issues to tasks
Right-click a task, then click the Link Jira issue menu.
If you want to connect to a new Jira site,
Click the “+“ icon.
Select the site you want to connect to. Then click the Accept button.
Search and pick an issue you want to link to.
Click the Link button.
Click the refresh icon.