  • Durations don’t include nonworking days and hours.

  • Gantt charts skip nonworking days and hours when setting start dates.

...

How to configure the working calendar

  1. Go to edit mode of the Gantt chart.

  2. Open the configuration panel.

  3. Switch tab to calendar.

  4. Edit working days, working hours, and extra holidays.

  5. Close the configuration panel by clicking the update button.

...

Relation between working days and duration units

Info

Please note working days affects the meaning of duration units.

...

1 Quarter equals the number of days in 3 months. And 1 Year equals the number of days in 12 months.

Example

Your Gantt chart has 5 working days as Monday, Tuesday, Wednesday, Thursday, and Friday like the image below.

...