Effort mode | If you revise duration | If you revise units | If you revise effort |
---|---|---|---|
Fixed Duration | Effort is recalculated. | Effort is recalculated. | Units are recalculated. |
Fixed Duration (Effort Driven) | Units are recalculated. | Units are recalculated. | |
Fixed Units | Effort is recalculated. | Effort is recalculated. | Duration is recalculated. |
Fixed Units (Effort Driven) | Effort is recalculated. | Duration is recalculated. | Duration is recalculated. |
Fixed Effort | Units are recalculated. | Duration is recalculated. | Duration is recalculated. |
Use case: ⛳️ Auto-scheduling with Gantt Chart Planner for Confluence