With WBS Gantt-Chart, holidays and non-working days are taken into account when creating/modifying plans. Follow these steps to configure non-working days.

  1. WBS Gantt-Chart ⇒ Choose Gantt Configure.

  2. Click Edit of Calendar

...

  1. Edit holiday calendar settings:

...

If there are no regular holidays, check Irregular holidays;

...

If there are regular holidays, select 1st regular holiday, or 2nd regular holiday, according to the number of non-working days;

...

    1. Choose using shared calendar or Gantt individual settings calendar

    2. Check the non-working days in Regular holiday

    3. Choose Week Number style (US or ISO-8061)

    4. For individual holidays

      1. Enter them to the Holiday list

      2. Or hit “Import Holidays” to import from Google Calendar. Choose Year and Country then click Import

    5. Click Update.

You’ve now completed the basic configuration. Next, let’s try managing a project.

...