This is how to configure settings for viewing the progress rate on WBS Gantt-Chart for Jira.

  1. WBS Gantt-Chart ⇒ Choose Gantt Configure.

  2. Click Edit of Issues

  3. Editing the progress rate (% done):

    1. If you want to edit the progress rate on WBS Gantt-Chart for Jira, select Use specified fields.

    2. If you want to automatically calculate the progress rate from time tracking (estimate of time remaining and time recorded), select Calculate automatically from time tracking.

  4. Click Update.

Next, learn how to configure versions.

...

Configuring version settings