Viewing due dates

The due date set for an issue is indicated by a red line on the Gantt chart. 

You can also check the due date column in the WBS.

Viewing task delays

Warning alerts are useful for telling you if an issue has started or completed as planned. If there is a colored “!” on the left-hand side of the WBS, that means there is information about the status of the issue.

Info

Since version 1.1.34-AC, alert settings can be freely changed.
Below are the default settings.

Warning

Explanation

Green

3 days prior to the start date

Yellow

Has not started yet - planned start date has passed

Red

Has not completed - planned finish date has passed

Image RemovedImage Added

Clicking a warning alert will show the corresponding Gantt bar.

Image RemovedImage Added

Gantt alert settings