You can check on the plan display whether an issue has started or completed as planned.

Look at the warning alerts on the far left-hand side of the WBS.

...

Icon

...

Description

...

This indicates that a task that should have been started has not yet been started.

...

This indicates that a task that should have been completed has not yet been completed.

Instruct assignees to deal with these tasks in order of priority.Please see the following page for details.

Viewing due dates and task delays

Check progress rateĀ 

If you are currently working on a task that is behind plan, you can check the progress rate, by looking at the progress rate displayed on the Gantt bar. If the bar is to the left of the current date line, the task is behind plan. Instruct assignees to make up the delay.

...