When displaying WBS Gantt charts, you need to set the maximum number of issues that can be displayed on the screen.

If you set this maximum at a high level, the processing time may be longer than expected with a correspondingly increased load on the server if you try to display a large number of issues on screen.

You should adjust the value you input to take account of the specifications of the server on which Jira is running and the number of users.

  1. Jira Setting ⇒ Apps 

  2. Select Issue in WBS Gantt-Chart

  3. Change the numerical value for the maximum number of displayable issues

  4. Click Update

...