Question

When adjusting issue details (such as start/end dates, progress) in the WBS Gantt - Chart and then saving, unrelated issues can also be updated with spurious values in these fields. This is the correct and expected behavior?

Answer

These updates on unrelated issues it is a specification required to the Auto Calculate Percent Done option to work properly. An explanation is described below:

...