Cloud | Server/Data Center (Latest version) | |||
---|---|---|---|---|
Calendar | Gantt owners can choose from the following options:
| Individualized settings for each Gantt | ||
User configuration |
|
| ||
Quick filter | Available | Not available | ||
Dependency column | Available | Not available | ||
Task order | Keep the order for each Project | Keep the order for each Gantt | ||
Available additional columns | Gantt column settings for 9.14 | |||
Issue detail view | Displayed on the dialog | Displayed on the right side of the Gantt Chart screen | ||
Job Scheduler | Not available | Available | ||
Convert standard issue to Issue template | Not available | Available | ||
Language |
|
| ||
Project side bar menu | Not available | AvailableYou can display a Gantt linked to the project. | The project and its issues are displayed directly on the Gantt chart. | |
Issues that cannot be retrieved by the Jira issue filter | Not displayed | If the issue is a parent or ancestor issue of an issue obtained with the Jira issue filter, it will be complemented and displayed. | ||
Storage format | ||||
Gantt-Chart data (start date, finish date, baseline, progress) | Jira administrators can choose from the following options:
| Jira field | ||
Hierarchy/dependency | Jira administrators can choose from the following options:
| Jira issue link | ||
Template | App’s own data | Jira issue |
...