The content of this Space is not the latest version of WBS Gantt-Chart for Jira.
We have separate Space for each version of the product. If the version you are using differs from the one in this Space title, please find the correct one from the below page. https://ricksoft-support.atlassian.net/wiki/spaces/WGC/overview



You are viewing documentation for WBS Gantt-Chart for Jira Server and Data Center. For Cloud, see WBS Gantt-Chart for Jira Cloud.
If you notice that the content is incorrect, please report it here.


Skip to end of metadata
Go to start of metadata

You are viewing an old version of this page. View the current version.

Compare with Current View Page History

« Previous Version 2 Next »

On this page:



Importing Microsoft Project files to Jira

You can import tasks from Microsoft Project as Jira issues by clicking DataMS Project import on the operations bar. 
In order to use this function, you need to have global administrator permission to "Bulk change" issues .

Each Microsoft Project field is imported as Jira issue field with the following conversion table. The destination Jira field of the planned dates (Start Date, Finish Date, Baseline Start Date, and Baseline Finish Date) and % Complete varies depending on the configurations in the WBS Gantt-Chart for Jira.

Microsoft Project fieldJira fieldNotes

WBS code

SummaryWBS code and Task name are combined under Summary. 
Task name
MemoDescription
Start dateField configured as Start Date in WBS Gantt-Chart

If read-only (non-editable) fields such as Created and Sprint are configured in WBS Gantt-Chart, those values will not be imported. 

End dateField configured as Finish Date in WBS Gantt-Chart
Baseline startField configured as Baseline Start Date in WBS Gantt-Chart
Baseline endField configured as Baseline Finish Date in WBS Gantt-Chart
% complete% done

If % done field is configured as "Calculate with time tracking automatically" or "Calculate with specific fields automatically" in WBS Gantt-Chart, those values will not be imported. 

WorkOriginal estimate
Remaining workRemaining estimate
Resource Assignee

Searches users registered in Jira in order of "Username" and "Full name." If there is a match, the matched user is selected as the assignee.
If there is no matching user, the user who performs the import is selected as the assignee.

The import will fail if the selected user does not have "Assignable" permission.


Reporter

Configures the user who performs the import as the reporter.


CreatedConfigures the imported date.

PriorityConfigures the default priority.



Unable to render {include} The included page could not be found.

  • No labels