/
Viewing issue dependencies

You are viewing documentation for WBS Gantt-Chart for Jira Cloud. For Server or Data Center, choose from documentation home.


Viewing issue dependencies

You can check for issue dependencies by looking at the blue arrows displayed between the Gantt bars. If there is a blue arrow from a predecessor issue pointing towards a successor issue, this indicates that the successor issue depends on the predecessor issue.

 

Types of task links or dependencies

There are four types of task links as follows:

Type

Dependency

Type

Dependency

Start-to-Start

A successor task cannot start until its predecessor task starts.

Start-to-Finish

A successor task cannot finish until its predecessor task starts.

Finish-to-Start

A successor task cannot start until its predecessor task finishes.

Finish-to-Finish

A successor task cannot finish until its predecessor task finishes.

Related content

Viewing the hierarchy structure
Viewing the hierarchy structure
Read with this
Create, edit, and delete dependency
Create, edit, and delete dependency
More like this
Viewing the critical path
Viewing the critical path
Read with this
Viewing the resource view
Viewing the resource view
Read with this
Hierarchy and Dependency on Issue detail view
Hierarchy and Dependency on Issue detail view
More like this