You are viewing documentation for WBS Gantt-Chart for Jira Cloud. For Server or Data Center, choose from documentation home.


Standard columns

Drag

This is the column to drag when manipulating WBS rows for manual sorting and hierarchy relationship manipulation.

When the mouse cursor hovers over a cell in this row, the mouse cursor design changes.

WBS Code (#)

This is the outline number to be given to the task in the WBS.
It will be updated when you reorder tasks by drag and drop or when you perform Renumber WBS code operations.

Alert

This is a column to warn of delays in the progress of the issue.
For more information on the alerts that appear, please see Analysis tools and functions .

Project/Version/Issue

This column displays the name of each project, version, and issue that appears in the WBS.

It is a link, and clicking on the name of a project or version will take you to the Jira page for that project or version.
Clicking on the name of the issue will bring up a dialog with the issue details view.

Key

This column displays the key to the Jira issue.

Assignee

This column displays the assignee field of the Jira issue.

Units

This is the column that shows what percentage of the working hours the assignee of the issue has allocated to the task from the start date to the finish date.

If the assignee does no work other than Task A, then Task A will be 100%.

If the Duration-Effort Adjustment column is set to 'Units adjusts', the value in this column will be automatically calculated using the Effort / Duration formula, and manual editing will be disabled.

Priority

This column displays the value of the priority field of the Jira issue.

Status

This column displays the value of the status field of the Jira issue.

Start

This column is used to display the start date and time of the task.

As for the time, if it is the same as the start time set in the Working Time setting, it will be omitted from the display in the cell.

Global Calendar settings

Finish

This column is used to display the finish date and time of the task.

As for the time, if it is the same as the finish time set in the Working Time setting, it will be omitted from the display in the cell.

Global Calendar settings

If the Duration-Effort Adjustment column is set to 'Duration adjusts', the value in this column will be automatically calculated using the value of the start date and the value of Duration, and manual editing will be disabled.

Duration

This column displays the duration from Start to Finish.

If the Duration-Effort Adjustment column is set to 'Duration adjusts', the value in this column will be automatically calculated using the Effort / Units formula, and manual editing will be disabled.

%done

This column represents the %done (progress rate) of the task.

Predecessor

This column displays the keys of the predecessor issues that have dependencies with the issue.

Successor

This column displays the keys of the successor issues that have dependencies with the issue.

Due Date

This column displays the due date field of the Jira issue.

Manually Scheduled

This column is used to select the scheduling mode for the issue.
If Manually scheduled is Yes, the issue will not be automatically rescheduled when its predecessor or child issues are rescheduled.

Effort

This column displays the sum of the Remaining estimate and the Time Spent on the issue.
In the Project, Version, and parent issue row, the aggregated value of the leaf issue's efforts will be displayed.

If the Duration-Effort Adjustment column is set to 'Effort adjusts', the value in this column will be automatically calculated using the Duration * Units formula, and manual editing will be disabled.

Users don’t have permission to edit time tracking.
Effort column becomes read-only. If Duration-Effort Adjustment is Effort adjusts, effort adjusts are disabled.

Duration-Effort Adjustment

This column is used to select the mode of recalculation for duration, effort, and units.
You can select from the following four modes.

Mode

Description

Mode

Description

Manual

This mode allows the user to manually enter the Duration, Units, and Effort values.

Effort adjusts

This mode automatically calculates the value of the Effort column using the Duration value * Units value formula.
Manual editing of the Effort column will be disabled.

Example

  • Duration = 8 hours

  • Units = 50%

→ Effort = 8 hours * 50% = 4 hours

Duration adjusts

This mode automatically calculates the value of the Duration column using the Effort value / Units value formula.
Manual editing of the Duration column will be disabled.

The Finish column is also disabled for manual editing, since the values of Start and Duration automatically determine the value of Finish.

Example

  • Effort = 16 hours

  • Units = 25%

→ Duration = 16 hours / 25% = 64 hours

Units adjusts

This mode automatically calculates the value of the Units column using the Effort value / Duration value formula.
Manual editing of the Units column will be disabled.

The default value for this column can be changed in the Gantt settings.

Gantt issue settings

Â