Information on the Gantt chart display
Displaying the planned Gantt bar of the currently selected row
Select a row and do one of the following with the row on WBS side being displayed in yellow:
- Click Jump to Gantt Bar on the operations toolbar
- Click Jump to Gantt Bar in the context menu
- Press keyboard shortcut b
If the start date in the target row is already entered, the Gantt chart jumps to the position of the start date. If only finish date is entered, the Gantt chart jumps to the finish date.
Displaying today's date
Click Today on the operations toolbar.
Time display units and time periods (display period)
Click on << or >> on the toolbar. The time period moved forward or backward depends on the time unit displayed .
Time display unit | Display period |
---|---|
Day | 7 days |
Week | 5 weeks |
Month | 3 months |
Quarter | 4 quarters |
Year | 5 years |
Changing a display unit
- Click the current Unit on the operations bar.
- Select one of the Units in the menu.
Time display unit | Display period |
---|---|
Day | 70 days |
Week | 30 weeks |
Month | 12 months |
Quarter | 20 quarters |
Year | 25 years |
Bird's-eye view | The Gantt chart spans all Gantt bars |
Two ways of displaying units for weeks
Weeks can be displayed in two ways: either by the start date of the week or the number of the week.
Display of fiscal year
Quarters are displayed based on the starting month of the fiscal year that is set. For example, if the start month of the fiscal year is March, the first quarter (Q1) is March to May.