Configuring the holiday calendar
With WBS Gantt-Chart, holidays and non-working days are taken into account when creating/modifying plans. Follow these steps to configure non-working days.
- ⇒ Choose Add-ons.
- Select Calendars.
- Select (Default)Â project Details.
- Click Edit Calendar.
- Edit holiday calendar settings:
- If there are no regular holidays, check Irregular holidays;
- If there are regular holidays, select 1st regular holiday, or 2nd regular holiday, according to the number of non-working days;
- For individual holidays, enter each day under Holiday in the format YYYY-MM-DD;
- Click Update.
You’ve now completed the basic configuration. Next, let’s try managing a project.