The content of this Space is not the latest version of WBS Gantt-Chart for Jira.
We have separate Space for each version of the product. If the version you are using differs from the one in this Space title, please find the correct one from the below page.
https://ricksoft-support.atlassian.net/wiki/spaces/WGC/overview
You are viewing documentation for WBS Gantt-Chart for Jira Server and Data Center. For Cloud, see WBS Gantt-Chart for Jira Cloud.
If you notice that the content is incorrect, please report it here.
Importing from Microsoft Project
Importing Microsoft Project files to Jira
If you are using Jira 8.4.0 - 8.4.1 Data Center, using this feature will cause an error and will not import issues.
This problem is caused by the following bugs in Jira and has been fixed in Jira 8.4.2 Data Center.
https://jira.atlassian.com/browse/JRASERVER-69968
You can import tasks from Microsoft Project as Jira issues by clicking Data ⇒ MS Project import on the operations bar.
In order to use this function, you need to have global administrator permission to "Bulk change" issues .
Each Microsoft Project field is imported as Jira issue field with the following conversion table. The destination Jira field of the planned dates (Start Date, Finish Date, Baseline Start Date, and Baseline Finish Date) and % Complete varies depending on the configurations in the WBS Gantt-Chart for Jira.
Microsoft Project field | Jira field | Notes |
---|---|---|
WBS code | Summary | WBS code and Task name are combined under Summary. |
Task name | ||
Memo | Description | |
Task mode | Manual mode (WBSGantt) | When the Task mode is "manually schedule", the value of Manual mode (WBSGantt) is set as Yes. |
Start date | Field configured as Start Date in WBS Gantt-Chart | If read-only (non-editable) fields such as Created and Sprint are configured in WBS Gantt-Chart, those values will not be imported. |
Finish date | Field configured as Finish Date in WBS Gantt-Chart | |
Baseline start | Field configured as Baseline Start Date in WBS Gantt-Chart | |
Baseline finish | Field configured as Baseline Finish Date in WBS Gantt-Chart | |
% complete | % done | If % done field is configured as "Calculate with time tracking automatically" or "Calculate with specific fields automatically" in WBS Gantt-Chart, those values will not be imported. |
Work | Original estimate | |
Remaining work | Remaining estimate | |
Resource | Assignee | Searches users registered in Jira in order of "Username" and "Full name." If there is a match, the matched user is selected as the assignee. The import will fail if the selected user does not have "Assignable" permission. |
Deadline | Due date | |
Reporter | Configures the user who performs the import as the reporter. | |
Created | Configures the imported date. | |
Priority | Configures the default priority. |