The content of this Space is not the latest version of WBS Gantt-Chart for Jira.
We have separate Space for each version of the product. If the version you are using differs from the one in this Space title, please find the correct one from the below page.
https://ricksoft-support.atlassian.net/wiki/spaces/WGC/overview
You are viewing documentation for WBS Gantt-Chart for Jira Server and Data Center. For Cloud, see WBS Gantt-Chart for Jira Cloud.
If you notice that the content is incorrect, please report it here.
Jira custom field, issue type, and issue link created by WBS Gantt-Chart for Jira
Custom field
Name | Type | Notes |
---|---|---|
Start date (WBSGantt) | Date picker | This field is used by default to store the start date of the plan. |
Finish date (WBSGantt) | Date picker | This field is used by default to store the finish date of the plan. |
Baseline start date (WBSGantt) | Date picker | This field is used by default to store the baseline start date of the plan. |
Baseline finish date (WBSGantt) | Date picker | This field is used by default to store the baseline finish date of the plan. |
Progress (WBSGantt) | Number field | This field is used by default to store the progress of the plan. |
Units (WBSGantt) | Number field | This field is used to store the work execution rate of the issue. |
Manually scheduled (WBSGantt) | Radio buttons | This field is used to allow only manual plan changes, without automatic adjustment of the plan in conjunction with the plan change of the child issue or predecessor issue. |
Milestone (WBSGantt) | Radio buttons | This field is used to treat issues as milestones. |
These custom fields are not created when WBS Gantt-Chart for Jira is installed.
It is created at the timing when the custom field is needed, such as when the WBS or Gantt chart screen is displayed for the first time or when the setting screen is displayed.
Even if these custom fields are deleted, they will be created again when WBS Gantt-Chart for Jira needs that custom field.
Issue type
Name | Notes |
---|---|
Issue template (WBSGantt) | This issue type is used to organize issue groups with parent-child relationships and plans set as templates. |
This issue type is not created when WBS Gantt-Chart for Jira is installed.
It is created at the timing when the issue type is needed, such as when the WBS or Gantt chart screen is displayed for the first time or when the setting screen is displayed.
Even if the issue type is deleted, they will be created again when WBS Gantt-Chart for Jira needs that custom field.
Issue link type
Name | Outward description | Inward description | Notes |
---|---|---|---|
Hierarchy link (WBSGantt) | Contains | Is contains in | This issue link type is used by default to express and store the parent-child relationship between issues. |
Start-to-Start link (WBSGantt) | Linked issue can start after this issue starts. | Cannot start until linked issue starts. | This issue link type is used by default to express and store the Start-to-Start link dependency between issues. |
Start-to-Finish link (WBSGantt) | Linked issue cannot finish until this issue starts. | Cannot finish until linked issue starts. | This issue link type is used by default to express and store the Start-to-Finish link dependency between issues. |
Finish-to-Start link (WBSGantt) | Linked issue cannot start until this issue finishes. | Cannot start until linked issue finishes. | This issue link type is used by default to express and store the Finish-to-Start link dependency between issues. |
Finish-to-Finish link (WBSGantt) | Linked issue cannot finish until this issue finishes. | Cannot finish until linked issue is finished. | This issue link type is used by default to express and store the Finish-to-Finish link dependency between issues. |
Issue template (WBSGantt) | Subordinate issue | Issue template | This issue link type is used to identify issues grouped together as templates. They are not displayed on the issue detail view and issue link type setting screens. |
These issue link types are not created when WBS Gantt-Chart for Jira is installed.
It is created at the timing when the issue link type is needed, such as when the WBS or Gantt chart screen is displayed for the first time or when the setting screen is displayed.
Even if these issue link types are deleted, they will be created again when WBS Gantt-Chart for Jira needs that custom field.
Issue link type is created according to Jira's system default language. Therefore, the name and description of the link may be different from the above.
If you are using Jira 8.2.0 - 8.2.3, due to the issue of Jira (JRASERVER-69388), the following issue link types are created with incorrect names and descriptions.
- Start-to-Start link (WBSGantt)
- Start-to-Finish link (WBSGantt)
- Finish-to-Start link (WBSGantt)
- Finish-to-Finish link (WBSGantt)
From the top of the issue link above, those in which the numbers 0, 1, 2, and 3 are used in the Name in the screenshot below apply. Please refer to the table on this page and press the Edit button to make corrections.