Creating and deleting a dependency
Creating and deleting a dependency
On this page:
Creating a dependency
Dragging the edge of an issue to the edge of another issue creates a dependency between the two issues.
- Move the cursor on the Gantt bar of a predecessor issue.
- Drag the connector.
- Drop on the connector of the successor issue Gantt bar.
A dependency cannot be created if issues have a parent-child relationship, or if the two issues are identical. Also, if a connector is not displayed, the settings do not allow to create that kind of dependency.
Deleting a dependency
Delete from the contextual menu of the issue.
- Right-click on the issue.
- Delete dependency ... ⇒ Select the dependency you want to delete
Unable to render {include} The included page could not be found.
, multiple selections available,
Related content
Creating plans, baselines, and due dates
Creating plans, baselines, and due dates
Read with this
Global Issue settings
Global Issue settings
More like this
Information on the WBS display
Information on the WBS display
Read with this
Terms and concepts
Terms and concepts
More like this
Tips for advanced users
Tips for advanced users
Read with this
Create Jira issues from Gantt Chart tasks
Create Jira issues from Gantt Chart tasks
More like this