Gantt holiday calendar settings

On this page:



What is the holiday calendar?

In WBS Gantt-Chart:

  • Regular (default) holidays are shown in gray.
  • Project holidays are shown in green.

Holidays are taken into consideration when project start and finish dates are set. All holidays are managed in WBS Gantt-Chart's holiday calendar.

Holiday calendar example

This is an example of the holiday calendar, showing two scenarios, A and B, as follows:

Conditions:

Scenario A


Yes / No
Regular holidays-
HolidaysNo

Scenario B


Yes / No
Regular holidaysSaturday, Sunday
Holidays

 

Note:  is Monday.

Issue values


Value
Start date

 

Finish date

 

Duration2 days

Operations

Drag-and-drop the Gantt bar so the issue starts on . 

Results

Scenario A

This scenario does not have holidays, so the issue values are as follows:


Value
Start date

 

Finish date

 

Duration2 days

Scenario B

In this scenario,  ,  , and  will not be counted since they are defined as holidays.


Value
Start date

 

Finish date

 

Duration2 days

Confirm holiday calendar settings

Click Calendars on the left-hand side of the Gantt configuration screen.

Holiday calendar items

Regular holidays

Check the box for the day of the week to be a fixed holiday.

Holidays

This is a list of the dates you have registered as holidays. 

Update holiday calendar

  1. Click Edit on the upper right-hand side of the holiday calendar configuration screen.
  2. Check the box for Regular holidays.
  3. Enter specific holidays using YYYY-MM-DD format. Enter one date per line.
  4. Click Update.



Unable to render {include} The included page could not be found.