Verifying assigned issues
Verifying assigned issues
First, verify your assigned issues. There are two ways to do this.
Verify from Gantt
Look at the Gantt notified to you by the project manager. Open the WBS, and look for the issues which have been assigned to you.
After you’ve opened the Gantt once, you’ll be able to open it again in future by doing this:
WBS Gantt-Chart ⇒ Select Gantt name
Verify from unresolved issues
You can also display issues that have been assigned to you but not yet completed. If you do this, only the issues which are specifically assigned to you will be displayed in WBS Gantt-Chart.
WBS Gantt-Chart ⇒ Select Your assigned issues (unresolved)
, multiple selections available,
Related content
Error Occurs When Updating Restricted Issues in Team-Managed Projects: "You do not have enough permissions to edit issues!"
Error Occurs When Updating Restricted Issues in Team-Managed Projects: "You do not have enough permissions to edit issues!"
More like this
Error Occurs When Updating Restricted Issues in Team-Managed Projects: "You do not have enough permissions to edit issues!"
Error Occurs When Updating Restricted Issues in Team-Managed Projects: "You do not have enough permissions to edit issues!"
More like this
Tutorial: Getting started as a project member
Tutorial: Getting started as a project member
Read with this
Required Jira Settings for Proper Functioning of WBS Gantt-Chart for Jira
Required Jira Settings for Proper Functioning of WBS Gantt-Chart for Jira
More like this
Configuring the progress rate
Configuring the progress rate
Read with this
Global Issue settings
Global Issue settings
More like this