Updating and calculating the progress rate (percent done)

You are viewing documentation for WBS Gantt-Chart for Jira Cloud. For Server or Data Center, choose from documentation home.


Updating and calculating the progress rate (percent done)

Basic method for updating the progress rate 

Click % Done to open Edit mode. Then you can either click the up/down arrows or directly enter a value.

However you cannot edit the progress rate for:

  • A project or version

  • Issues in gray color

Auto-calculating parent issue progress rate 

You may want to synchronize the progress rate between parent and child issues. This would mean, for example, that when the progress rate of a child issue is 100%, the parent issue's progress rate will also be 100%. You can do this by Enabling the “Calculate Parent percent done from Children” option in the issue setting in the gantt configuration.

Refer Gantt issue settings | Calculate Parent percent done from Children for more detail.

 

 

The calculation of the progress rate is based on time spent and duration. For example

  • Issue A has a duration of 1 day with 100% done

  • Issue B has a duration of 2 days with 50% done

The total progress rate of parent issue would be:

(100% * 1 day + 50% * 2 days) / (1 day + 2 days) = 66% (Decimals are rounded down)

 

There is a special case.

  • The progress rate of the parent ticket is calculated as 100%

  • However, there is a child ticket with a blank duration and progress rate < 100%

In this scenario, the parent's progress rate will be adjusted to 99%

 



Related content

Gantt issue settings
Gantt issue settings
Read with this
Updating and calculating the progress rate (percent done)
Updating and calculating the progress rate (percent done)
More like this
Global Issue settings
Global Issue settings
Read with this
Updating and calculating the progress rate (percent done)
Updating and calculating the progress rate (percent done)
More like this
Terms and concepts
Read with this
Updating and calculating the progress rate (percent done)
Updating and calculating the progress rate (percent done)
More like this