With WBS Gantt-Chart, holidays and non-working days are taken into account when creating/modifying plans. Follow these steps to configure non-working days.
- WBS Gantt-Chart ⇒ Choose Gantt Configure.
- Click Edit of Calendar.
- Edit holiday calendar settings:
- If there are no regular holidays, check Irregular holidays;
- If there are regular holidays, select 1st regular holiday, or 2nd regular holiday, according to the number of non-working days;
- For individual holidays, enter each day under Holiday in the format YYYY-MM-DD;
- Click Update.
You’ve now completed the basic configuration. Next, let’s try managing a project.