What is the holiday calendar?
In WBS Gantt-Chart:
- Regular (default) holidays are shown in gray.
- Project holidays are shown in green.
Holidays are taken into consideration when project start and finish dates are set. All holidays are managed in WBS Gantt-Chart's holiday calendar.
Holiday calendar example
This is an example of the holiday calendar, showing two scenarios, A and B, as follows:
Conditions:
Scenario A
Yes / No | |
---|---|
Regular holidays | - |
Holidays | No |
Scenario B
Yes / No | |
---|---|
Regular holidays | Saturday, Sunday |
Holidays |
|
Note: is Monday.
Issue values
Value | |
---|---|
Start date |
|
Finish date |
|
Duration | 2 days |
Operations
Drag-and-drop the Gantt bar so the issue starts on .
Results
Scenario A
This scenario does not have holidays, so the issue values are as follows:
Value | |
---|---|
Start date |
|
Finish date |
|
Duration | 2 days |
Scenario B
In this scenario, , , and will not be counted since they are defined as holidays.
Value | |
---|---|
Start date |
|
Finish date |
|
Duration | 2 days |
Confirm holiday calendar settings
Click Calendars on the left-hand side of the Gantt configuration screen.
Holiday calendar items
Regular holidays
Check the box for the day of the week to be a fixed holiday.
Holidays
This is a list of the dates you have registered as holidays.
Update holiday calendar
- Click Edit on the upper right-hand side of the holiday calendar configuration screen.
- Check the box for Regular holidays.
- Enter specific holidays using YYYY-MM-DD format. Enter one date per line.
- Click Update.