Exporting to Microsoft Project
...
WBS Gantt-Chart for Jira | Microsoft Project field | Notes |
---|---|---|
Summary | Task name | |
Assignee | Resource name |
|
Units | ||
Start date | Start date | |
Finish date | Finish date | |
Baseline start date | Standard start date | |
Baseline finish date | Standard finish date | |
% done | % complete | Uses the value of the field configured as "% done" in WBS Gantt-Chart for Jira However, in Microsoft Project, the % completion rate of a summary task is automatically calculated including accumulated % completion of child tasks as well. Therefore the value shown may differ from % done in WBS Gantt-Chart for Jira. |
Due date | Deadline |
Limit
The export process will time out if it is not completed within 30 seconds.
Therefore, timeouts may occur when exporting large Gantt-Chart with many issues.