Exporting to Microsoft Project

You can export projects, versions and issues displayed in WBS Gantt-Chart as XML files that are readable in Microsoft Project by clicking ToolsMS Project export on the operations bar.

This feature supports exporting hierarchies and dependencies (including lags), as well as several fields.

The correspondence table between the Jira and Microsoft Project fields is provided below.

WBS Gantt-Chart for Jira

Microsoft Project field

Notes

Summary

Task name


Assignee 

Resource name

  • Makes the assignee's username and units as the output.

  • If the units is 0, Microsoft Project specifies the duration of the task as 0 days as a default. Therefore tasks with no milestones and 0% units are exported with a 1% units.

  • If square brackets are used for the full name of the assignee, convert to parentheses. In Microsoft Project, you cannot use square brackets for resource names.

Units

Start date

Start date


Finish date

Finish date


Baseline start date

Standard start date


Baseline finish date

Standard finish date 


% done 

% complete

Uses the value of the field configured as "% done" in WBS Gantt-Chart for Jira

However, in Microsoft Project, the % completion rate of a summary task is automatically calculated including accumulated  % completion of child tasks as well. Therefore the value shown may differ from % done in WBS Gantt-Chart for Jira.

Due date

Deadline



Additional Help

If you have any questions please feel free to ask a member of the Atlassian community!

Add the tag "addon-jp.ricksoft.plugins.wbsgantt-for-jira" when you ask a question.

Ask the community

  • No labels