This is how to configure settings for viewing the progress rate on WBS Gantt-Chart for Jira.

  1. ⇒ Choose Add-ons.
  2. Select Issue.
  3. Click Edit issue type (Default). 
  4. Editing the progress rate (% done):
    1. If you want to edit the progress rate on WBS Gantt-Chart for Jira, select Use specified fields.
      1. If you want to set the progress rate to 100% when an issue is resolved, check Automatically set progress to 100% once the issue is resolved.
      2. If you want to set the progress rate to 0% when you reopen an issue, check Automatically set progress to 0% when you reopen the issue.
    2. If you want to automatically calculate the progress rate from time tracking (estimate of time remaining and time recorded), select Calculate automatically from time tracking.
    3. To automatically calculate the progress level from two specified fields, select Calculate automatically from specified fields.
      1. Select the numerator field for the numerator.
      2. Select the denominator field for the denominator.
  5. Click Update.

Next, learn how to configure versions.