Gantt holiday calendar settings

What is the holiday calendar?

In WBS Gantt-Chart:

  • Regular (default) holidays are shown in gray.

  • Project holidays are shown in green.

Holidays are taken into consideration when project start and finish dates are set. All holidays are managed in WBS Gantt-Chart's holiday calendar.

Holiday calendar example

This is an example of the holiday calendar, showing two scenarios, A and B, as follows:

Conditions:

Scenario A



Yes / No



Yes / No

Regular holidays

-

Holidays

No

Scenario B



Yes / No



Yes / No

Regular holidays

Saturday, Sunday

Holidays

Apr 3, 2017 

Note: Apr 3, 2017 is Monday.

Issue values



Value



Value

Start date

Mar 28, 2017 

Finish date

Mar 29, 2017 

Duration

2 days

Operations

Drag-and-drop the Gantt bar so the issue starts on Mar 31, 2017. 

Results

Scenario A

This scenario does not have holidays, so the issue values are as follows:



Value



Value

Start date

Mar 31, 2017 

Finish date

Mar 29, 2017 

Duration

2 days

Scenario B

In this scenario, Apr 1, 2017 , Apr 2, 2017 , and Apr 3, 2017 will not be counted since they are defined as holidays.



Value



Value

Start date

Mar 31, 2017 

Finish date

Apr 4, 2017 

Duration

2 days

Confirm holiday calendar settings

Click Calendars on the left-hand side of the Gantt configuration screen.

Holiday calendar items

Regular holidays

Check the box for the day of the week to be a fixed holiday.

Holidays

This is a list of the dates you have registered as holidays. 

Update holiday calendar

  1. Click Edit on the upper right-hand side of the holiday calendar configuration screen.

  2. Check the box for Regular holidays.

  3. Enter specific holidays using YYYY-MM-DD format. Enter one date per line.

  4. Click Update.