You are viewing documentation for WBS Gantt-Chart for Jira Cloud. For Server or Data Center, choose from documentation home.


Skip to end of metadata
Go to start of metadata

You are viewing an old version of this page. View the current version.

Compare with Current View Page History

« Previous Version 3 Next »

On this page:




Time display units and time periods (display period)

Click on << or >> on the toolbar. The time period moved forward or backward depends on the time unit displayed . 

Time display unitDisplay period
Day7 days
Week5 weeks
Month3 months
Quarter4 quarters
Year5 years





Displaying today's date

Click Today.



Changing a display unit

  1. Click the current Unit on the operations bar.
  2. Select one of the Units in the menu. 



Time display unitDisplay period
Day70 days
Week30 weeks
Month12 months
Quarter20 quarters
Year25 years
Bird's-eye view 

The Gantt chart spans all Gantt bars


Two ways of displaying units for weeks

Weeks can be displayed in two ways: either by the start date of the week or the number of the week.


Display of fiscal year

Quarters are displayed based on the starting month of the fiscal year that is set. For example, if the start month of the fiscal year is March, the first quarter (Q1) is March to May.


 









Additional Help

If you have any questions please feel free to ask a member of the Atlassian community!

Add the tag "addon-jp.ricksoft.plugins.wbsgantt-for-jira" when you ask a question.

Ask the community

  • No labels