When the number of tasks in a project increases, it becomes time-consuming to search for the schedule of important tasks.
To solve this issue, you can select only the key tasks and milestones and display them on a summarized timeline.

How to use summarized timeline

Display summarized timeline

  1. Open the Features menu dropdown

  2. Enable Show summarized timeline option

スクリーンショット 2024-09-30 18.10.15.png

 

スクリーンショット 2024-09-30 16.51.31.png

 

Select tasks/milestones to be displayed on the summarized timeline

  1. Open the Columns menu dropdown

  2. Enable Summarized Timeline column

  3. Turn on the summarized timeline checkbox for the important tasks you want to display in the summarized timeline

 