You are viewing documentation for WBS Gantt-Chart for Jira Cloud. For Server or Data Center, choose from documentation home.
Configuring the hierarchy, dependency, and scheduling
In WBS Gantt-Chart for Jira, you can use Jira issue links to maintain the hierarchical relationships and dependencies of issues, and use Jira issues to maintain various data such as start and finish dates.
Jira Setting ⇒ AppsÂ
Select Issue in WBS Gantt-Chart
Set the issue link type and Jira fields to be used in WBS Gantt-Chart for Jira.
Click Update