Information on the Gantt chart display

The content of this Space is not the latest version of WBS Gantt-Chart for Jira.
We have separate Space for each version of the product. If the version you are using differs from the one in this Space title, please find the correct one from the below page. https://rssupport.atlassian.net/wiki/spaces/WGC/overview


Information on the Gantt chart display

On this page:







Time display units and time periods (display period)

Click on << or >> on the toolbar. The time period moved forward or backward depends on the time unit displayed . 

Time display unit

Display period

Time display unit

Display period

Day

7 days

Week

5 weeks

Month

3 months

Quarter

4 quarters

Year

5 years









Displaying today's date

Click Today.





Changing a display unit

  1. Click the current Unit on the operations bar.

  2. Select one of the Units in the menu. 





Time display unit

Display period

Time display unit

Display period

Day

70 days

Week

30 weeks

Month

12 months

Quarter

20 quarters

Year

25 years

Bird's-eye view 

The Gantt chart spans all Gantt bars



Two ways of displaying units for weeks

Weeks can be displayed in two ways: either by the start date of the week or the number of the week.



Display of fiscal year

Quarters are displayed based on the starting month of the fiscal year that is set. For example, if the start month of the fiscal year is March, the first quarter (Q1) is March to May.